Changes to road access to the practice between Friday 4th July and Wednesday 9th July.
Update: Friday 4th July 2025
The road re-surfacing work has hit (literally) the mains water pipe so all work has stopped until Yorkshire Water comes to stop the leak. It seems that the plan is to leave a single file access to the practice carpark from Oakwood Lane. The access to Monagu Avenue at the bottom of Amberton Terrace will remain open in both directions.
On Monday 7th , they plan to continue to resurfacing at the top end (i,e., near the practice) so access will be from Montagu Avenue only.
On Tuesday 8th /Wednesday 9th they will resurface the lower half of Amberton Terrace so access will be from Oakwood Lane only.
By the end of Wednesday, the whole road should be fully re-surfaced.